January 8 1h 17m 55s Download (English) : 1. Opening remarks, Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), 2. Presentation from Ontario Power Generation Stream (English) : 1. Opening remarks, Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), 2. Presentation from Ontario Power Generation  
        
            January 8 1h 28m 49s Download (English) : 3. Presentation from CNSC Staff, Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Question Period Stream (English) : 3. Presentation from CNSC Staff, Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Question Period  
        
            January 8 2h 38m 33s Download (English) : 4. Michi Saagiig Nations Opening remarks, Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), 5. Presentation from Michi Saagiig Nations before the break Stream (English) : 4. Michi Saagiig Nations Opening remarks, Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), 5. Presentation from Michi Saagiig Nations before the break  
        
            January 8 1h 20m 50s Download (English) : 4. Closing of the hearing for January 8, 2025, Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP) Stream (English) : 4. Closing of the hearing for January 8, 2025, Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP)  
        
            January 9 1h 52m 07s Download (English) : 1. Opening remarks, Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), 2. Presentation from intervenors Stream (English) : 1. Opening remarks, Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), 2. Presentation from intervenors  
        
            January 9 1h 38m 18s Download (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentation from intervenors before the lunch break Stream (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentation from intervenors before the lunch break  
        
            January 9 2h 13m 54s Download (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentation from intervenors after the lunch break Stream (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentation from intervenors after the lunch break  
        
            January 9 1h 39m 06s Download (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentations from intervenors following the afternoon break Stream (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentations from intervenors following the afternoon break  
        
            January 10 1h 39m 01s Download (English) : 1. Opening remarks, Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentations from intervenors Stream (English) : 1. Opening remarks, Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentations from intervenors  
        
            January 10 1h 14m 37s Download (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentation from intervenors before the lunch break Stream (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentation from intervenors before the lunch break  
        
            January 10 1h 17m 29s Download (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentation from intervenors after the lunch break Stream (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentation from intervenors after the lunch break  
        
            January 10 33m 28s Download (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Final rounds of questions (including questions on written submissions), Closing of the public hearing Stream (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Final rounds of questions (including questions on written submissions), Closing of the public hearing  
        
            January 13 1h 29m 21s Download (English) : 1. Opening remarks, Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), 2. Presentations from intervenors Stream (English) : 1. Opening remarks, Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), 2. Presentations from intervenors  
        
            January 13 1h 23m 52s Download (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentation from intervenors before the lunch break Stream (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentation from intervenors before the lunch break  
        
            January 13 1h 43m 31s Download (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentation from intervenors after lunch break Stream (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentation from intervenors after lunch break  
        
            January 13 10m 27s Download (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentations from intervenors following the afternoon break Stream (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Presentations from intervenors following the afternoon break  
        
            January 13 18m 43s Download (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Final rounds of questions (including questions of written submissions), Closing of the public hearing Stream (English) : 3. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Final rounds of questions (including questions of written submissions), Closing of the public hearing  
        
            January 14 1h 25m 38s Download (English) : 1. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), 2. Rounds of questions (including questions on written submissions) Stream (English) : 1. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), 2. Rounds of questions (including questions on written submissions)  
        
            January 14 1h 41m 15s Download (English) : 1. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Rounds of questions before the lunch break (including questions on written submissions) Stream (English) : 1. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Rounds of questions before the lunch break (including questions on written submissions)  
        
            January 14 1h 34m 56s Download (English) : 1. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Rounds of questions after the lunch break (including questions on written submissions) Stream (English) : 1. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Rounds of questions after the lunch break (including questions on written submissions)  
        
            January 14 1h 22m 32s Download (English) : 1. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Final rounds of questions (including questions on writen submissions), Closing of the public hearing Stream (English) : 1. Ontario Power Generation Inc.: Application for a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project Site (DNNP), Final rounds of questions (including questions on writen submissions), Closing of the public hearing