Language selection

Search


Regulatory review status for the Wheeler River Project

CNSC Website User Survey

Share your experience in using our website by completing our survey. The survey should take you less than 10 minutes to complete.

The Commission has issued a licence to Denison Mines Corporation (Denison) authorizing it to prepare a site for and construct an in situ recovery uranium mining and processing operation – the Wheeler River Project – located in the Athabasca Basin in Saskatchewan, approximately 600 kilometres north of Saskatoon.

The licence, valid until February 28, 2031, does not authorize the operation of the facility to be constructed. Authorization to operate the facility would be subject to a future Commission licensing hearing and decision should Denison come forward with the relevant licence application.

If operation of the facility were to be authorized, the Wheeler River Project could potentially produce up to 5,400 tonnes of uranium oxide annually for up to 15 years. An environmental assessment (EA) for this project was completed under the Canadian Environmental Assessment Act, 2012, and the Commission concluded that the project was not likely to cause significant adverse environmental effects considering the proposed mitigation measures and follow-up monitoring measures.

Environmental assessment start date: May 31, 2019
Reference number80178

Timeline

Application submitted

Date Activity
July 4, 2023 The initial licence application for a licence to prepare site and construct a mine and mill was submitted.
November 22, 2024 The submitted application to prepare site and construct a uranium mine and mill was deemed sufficient by CNSC staff.

Assessments

Date Activity
May 31, 2019 Notice of commencement of the EA
May 31, 2019 Public comments invited on project description
December 2019 Commission hearing on the scope of the EA
December 20, 2019 Record of decision on the scope of the EA
March 20, 2020 Temporary suspension of the EA
January 25, 2021 Resumption of the EA
January 10, 2022 Notice of participant funding offering for draft environmental impact statement (EIS) review (1)
September 13, 2022 Webinar – CNSC regulatory review process
October 21, 2022 Denison submits draft EIS, passes CNSC conformity review
November 21, 2022 to March 21, 2023 The Federal Indigenous Review Team (FIRT) completes initial technical review and deems draft EIS incomplete
April 26, 2023 Spring Bulletin 2023
June 27, 2023 Public comments consolidated into detailed tables for response by the proponent and regulators
July 14, 2023 Denison submits responses to the FIRT’s information requests (IRs), fails CNSC completeness review
August 29, 2023 Denison re-submits responses to the FIRT IRs, passes CNSC completeness review
August 30 to December 5, 2023 The FIRT completes the technical review of Denison’s responses to IRs and deems them incomplete
December 8, 2023 Winter Bulletin 2023
February 10, 2024 Denison re-submits a draft EIS package and responses to IRs to the FIRT and CNSC completeness review passes
February 21, 2024 – October 11, 2024 The FIRT completes extended technical review of the Denison’s responses to IRs and deems incomplete
August 23, 2024 Summer Bulletin 2024
October 18, 2024 Denison re-submits responses to IRs to the FIRT, passes CNSC completeness review
October 25 to November 20, 2024 The FIRT completes the technical review of Denison’s responses to IRs and deems them complete
November 22, 2024 Denison submission of final EIS
December 24, 2024 CNSC staff acceptance of final EIS for the Wheeler River Project
February 3, 2025 Notice of participant funding offering (2)
February 27, 2025 Notice of public hearing
August 19, 2025

CNSC staff Commission member document and EA report available for public review (in English only)

October 8, 2025 Public Hearing Part 1
October 24, 2025 Public intervention deadline
October 29, 2025 Fall Bulletin 2025
December 8 to 11, 2025 Public Hearing Part 2

Public hearing

Date Activity
October 8, 2025 Application for a licence to prepare a site for and construct its Wheeler River mine and mill project (Part 1)
December 8 to 11, 2025 Application for a licence to prepare a site for and construct its Wheeler River mine and mill project (Part 2)

Commission decisions

Date Activity
February 19, 2026 Commission issues a site preparation and construction licence to Denison Mines Corp. for its Wheeler River Project

Licence issued

Date Activity
February 19, 2026 Site preparation and construction licence

Compliance activities

Date Activity
N/A

Contact

For general CNSC updates, subscribe to the CNSC’s mailing list. For information directly related to this project, please contact:

Environmental Assessment Division
Email: WheelerRiver@cnsc-ccsn.gc.ca
Telephone: 613-995-7948 or 1-800-668-5284

Mailing address: Canadian Nuclear Safety Commission
PO Box 1046 Stn B
Ottawa ON  K1P 5S9

Additional resources

Page details

Date modified: