Regulatory review status for the Rook I project
CNSC Website User Survey
Share your experience in using our website by completing our survey. The survey should take you less than 10 minutes to complete.
The Commission has issued a licence to NexGen Energy Ltd. (NexGen) authorizing it to prepare a site for and construct a uranium mine. The mine will be located on the Patterson Lake peninsula, in the southwestern Athabasca Basin in northern Saskatchewan, approximately 155 km north of the town of La Loche.
The licence, valid until March 31, 2036, does not authorize operation of the facility to be constructed. Authorization to operate the facility would be subject to a future Commission licensing hearing and decision should NexGen come forward with a relevant licence application.
An environmental assessment (EA) for this project was completed under the Canadian Environmental Assessment Act, 2012. The Commission concluded that the project was not likely to cause significant adverse environmental effects considering the proposed mitigation measures and follow-up monitoring measures.
Environmental assessment start date: May 2, 2019
Reference number: 80171
Timeline
|
Application submitted |
|
|---|---|
| February 14, 2019 | NexGen submits licence application and CNSC starts review of the application |
|
Assessments |
|
| May 2, 2019 | Notice of commencement of the EA |
| May 2, 2019 | Public comments invited on project description |
| February 2020 | Commission hearing on the scope of the EA |
| February 20, 2020 | Record of decision on the scope of the EA |
| May 25, 2020 | Notice of participant funding offering |
| June 13, 2022 | NexGen submits draft environmental impact statement (EIS) and licensing documentation |
| July 14 – October 12, 2022 | CNSC and federal Indigenous technical review of draft EIS and licensing documentation |
| July 14 – October 12, 2022 | Public comments invited on draft EIS |
| September 13, 2022 (tentative) | CNSC webinar – CNSC regulatory review process |
| November 10, 2022 | The CNSC completes initial review of draft EIS |
| November 18, 2022 | The Federal Indigenous Review Team (FIRT) completes a technical review and deems draft environmental impact statement (EIS) incomplete |
| September 5, 2023 | NexGen submits responses to information requests (IRs) |
| October 13, 2023 | CNSC staff conduct a completeness check and deem responses to IRs insufficient |
| October 31, 2023 | NexGen resubmits responses to IRs |
| November 15, 2023 | CNSC staff conduct a completeness check and determine that adequate information was provided |
| November 14, 2023 – February 12, 2024 | The FIRT completes technical review of revised draft EIS |
| May 22, 2024 | NexGen resubmits revised draft EIS |
| June 20, 2024 | CNSC staff conduct a completeness check and determine that adequate information was provided |
| June 21 – September 20, 2024 | The FIRT undertakes a technical review of the revised draft EIS |
| November 19, 2024 | The FIRT completes its technical review and all IR responses are deemed as accepted |
| November 29, 2024 | NexGen submits final EIS |
| November 29, 2024 – January 28, 2025 | CNSC staff undertake a review of the final EIS package |
| January 28, 2025 | CNSC staff complete review of final EIS package and deem final EIS acceptable |
| October 10, 2025 | CNSC staff licensing Commission member document and EA report available for public review |
| January 9, 2026 | Public intervention deadline |
|
Public hearing |
|
| November 19, 2025 | Part 1 of the 2-part public hearing on the Rook I Project |
| February 9–12, 2026 | Part 2 of the 2-part public hearing on the Rook I Project |
|
Commission decisions |
|
| February 20, 2020 | Record of decision on the scope of the EA |
| March 4, 2026 | Commission issues a licence to NexGen Energy Ltd. authorizing site preparation and construction of its Rook I Project |
|
Licence issued |
|
| March 4, 2026 | Site preparation and construction licence |
|
Compliance activities |
|
| December 12, 2024 | Administrative monetary penalty issued to NexGen Energy Ltd. |
Contact
For general CNSC updates, subscribe to the CNSC’s mailing list. For information directly related to this project, please contact:
Environmental Assessment Division
Email: ea-ee@cnsc-ccsn.gc.ca
Telephone: 613-995-7948 or 1-800-668-5284
Fax: 613-995-5086
Mailing address: Canadian Nuclear Safety Commission
P. O. Box 1046, Station B
Ottawa ON K1P 5S9
Page details
- Date modified: