Letter to Ontario Power Generation regarding Regulatory Hold Point 1
CNSC Website User Survey
Share your experience in using our website by completing our survey. The survey should take you less than 10 minutes to complete.
Regulatory Operations Branch
November 5, 2019
Mr. Dietmar Reiner
Senior Vice President, Nuclear Projects
Ontario Power Generation Inc.
1855 Energy Drive, 3C14
Courtice, ON L1E 0E7
SUBJECT: Darlington NGS - Unit 2 Return to Service: Request for CNSC Consent to Remove the Regulatory Hold Point Prior to Fuel Load
Dear Mr. Reiner:
The purpose of this letter is to respond to Ontario Power Generation’s (OPG) request [1] to remove Regulatory Hold Point (RHP-1), allowing fuel to be loaded in the refurbished Darlington Unit 2 reactor core.
Canadian Nuclear Safety Commission (CNSC) staff’s assessment [2, 3] concluded that OPG has met all the pre-requisites established by the Commission to remove RHP-1. Therefore, as the person authorized by the Commission and pursuant to Licence Condition 15.4 of the Darlington Nuclear Generating Station (DNGS) Power Reactor Operating Licence 13.01/2025, consent to remove RHP-1 is hereby granted and fuel may now be loaded into the Unit 2 core.
Yours sincerely,
Ramzi Jammal
Executive Vice-President and
Chief Regulatory Operations Officer
Regulatory Operations Branch
c.c: G. Frappier, N. Riendeau, C. Loreti, D. Desjardins, D. Nguyen, N. Abonasara, K. Hazelton, A. Mathai, C. Yacoub, Darlington Site Office
References:
- OPG Letter, D. Reiner and S. Gregoris to R. Jammal, “Darlington NGS Refurbishment – Unit 2 Return to Service: Request for CNSC Consent Prior to Fuel Load (RHP 1)”, November 4, 2019, NK38-CORR-00531-21109.
- CNSC staff document entitled: “Request by Ontario Power Generation Inc. to Remove Regulatory Hold Point for Prior To Fuel Load for Unit 2”, dated October 21, 2019.
- CNSC memorandum: “Removal of Regulatory Hold Point 1 – Prior to Fuel Load for Darlington NGS Unit 2”, Dated November 5, 2019.