Location: Bowmanville, Municipality of Clarington, ON
Summary
The Darlington project is for the site preparation, construction, operation, decommissioning and abandonment of up to four new nuclear reactors at the existing Darlington Site to generate approximately 4,800 megawatts of electricity to the Ontario grid.
Latest News
Darlington Joint Review Panel Activity to Date
Licensing Progress Details (Timelines are best estimates and are subject to change)
Environmental Assessment and Site Preparation |
||||
Project Milestone |
Responsibility |
Date |
Comment |
|
CNSC and other Federal Authorities |
Applicant |
|||
Ontario Power Generation applies for a Licence to Prepare Site (PDF) |
|
September |
|
|
Notice of Environmental Assessment (EA) posted Read Project Description (PDF) - in English only |
|
May |
Additional information was required to complete the Project Description. This was completed in 2007 and allowed the Environmental Assessment to start. |
|
Federal Minister of Environment refers EA to a Joint Review Panel (JRP) |
|
March |
|
|
Draft Environmental Impact Statement (EIS) Guidelines and JRP Agreement published for comments |
|
September |
|
|
Comment period on draft Environmental Impact Statement Guidelines and JRP Agreement Read Comments |
|
September |
Opportunity for the public, Aboriginal groups and other stakeholders to review and provide comments. |
|
|
March 2009 |
Finalized by the federal Minister of the Environment, in consultation with the President of CNSC, based on comments received. |
||
| Major Projects Management Office (MPMO) Project Agreement signed(source: MPMO) |
|
May |
An MPMO Project Agreement (source: CEAA) is an agreement between federal Deputy Ministers that outlines the process by which federal departments or agencies will carry out their particular roles or responsibilities during the federal regulatory review of a proposed major resource project. The agreement includes a timeline and schedule for the completion of the regulatory review with regular milestones to allow tracking of progress. |
|
Ontario Power Generation submits the EIS with documentation |
|
September |
|
|
|
October 2009 |
Appointed by the Minister of the Environment and the Governor in Council in consultation with the President of CNSC.
|
||
Notice of EIS review period (Source: CEAA) |
|
November |
JRP announces the start of the EIS review period with instructions to provide comments. |
|
Start of Public Comment Period Review of EIS, including public review Read comments (source: CEAA) |
|
November 2009 Below are the JRP requests for additional information from OPG during this public comment period. |
Six-month comment period** led by JRP, including conformity and technical review of the EIS and complete application for Licence to Prepare Site. Review opportunity for the JRP, public, Aboriginal groups and other stakeholder for comments. **Six-month comment period excludes time used by applicant to respond to JRP requests. The comment period is extended when there is a request for information by the JRP. The comment period’s end date is determined according to the amount of time the applicant requires to respond to the JRP’s request. |
|
Public notice of technical information session held on December 15, 2009 in Ottawa (source: CEAA Web site) Consult presentations and transcripts (source: CEAA Web site) |
|
December 2009 | JRP invited the public to attend a technical information about nuclear power plant designs based on three reactor technologies | |
Information Request 1: JRP letter of request for additional information (source: CEAA) |
Completed by JRP |
December 2009 | JRP sends a letter to Ontario Power Generation requesting additional information concerning the EIS and complete application for a Licence to Prepare a Site, submitted by Ontario Power Generation in September 2009 (source: Ontario Power Generation (OPG)) CNSC submits no Information Requests (IRs) to JRP |
|
| Ontario Power Generation responds in January to the JRP Information Request 1 of December 2009. (PDF) (Source: CEAA) |
|
January 2010 | Ontario Power Generation responds to JRP’s Information Request 1, concerning the EIS and application for a Licence to Prepare Site submitted by Ontario Power Generation in September 2009 (Source: OPG) | |
Information Request 2: JRP requests from Ontario Power Generation additional information regarding their EIS and complete application (source: CEAA) JRP letter of request for additional information (PDF) (source: CEAA) |
Completed by JRP |
February 2010 | JRP sends a letter to Ontario Power Generation requesting for additional information concerning the EIS and complete application for a Licence to Prepare a Site, submitted by Ontario Power Generation in September 2009 CNSC submits 40 EIS and 21 Licence to Prepare Site (LTPS) IRs to JRP (Source: CEAA) |
|
Ontario Power Generation responds in February and in March to the JRP Information Request 2 of February 2010. (PDF) (Source: CEAA) |
Completed by Ontario Power Generation (OPG) |
February and March 2010 | Ontario Power Generation responds to JRP’s Information Request 2, concerning the EIS and application for a Licence to Prepare Site submitted by Ontario Power Generation in September 2009 (Source: OPG) |
|
Information Request 3: JRP letter of request for additional information (PDF) (source: CEAA) |
Completed by JRP |
March 29, 2010 | JRP sends a letter to Ontario Power Generation requesting for additional information concerning the EIS and application for a Licence to Prepare Site submitted by Ontario Power Generation in September 2009 (Source: OPG) CNSC submits 4 EIS IRs to JRP (Source: CEAA) |
|
Ontario Power Generation responds in April to the JRP Information Request 3 of March 2010 (PDF) (Source: CEAA) |
Completed by Ontario Power Generation (OPG) |
April 21, 2010 | Ontario Power Generation responds to JRP’s Information Request 3, [concerning the EIS and application for a Licence to Prepare Site submitted by Ontario Power Generation in September 2009] (Source: OPG) |
|
Information Request 4: JRP letter of request for additional information (PDF) (source: CEAA) |
Completed by JRP |
April 28, 2010 | JRP sends a letter to Ontario Power Generation requesting for additional information concerning the EIS and application for a Licence to Prepare Site submitted by Ontario Power Generation in September 2009 (Source: OPG) CNSC submits no new IRs to JRP |
|
Ontario Power Generation responds in May and June to the JRP Information Request 4 of April 2010 (PDF) (Source: CEAA) |
Completed by Ontario Power Generation (OPG) |
May 28 and June 11, 2010 | Ontario Power Generation responds to JRP’s Information Request 4, concerning the EIS and application for a Licence to Prepare Site submitted by Ontario Power Generation in September 2009 (Source: OPG) |
|
Information Request 5: JRP letter of request for additional information (PDF) (source: CEAA) |
Completed by JRP |
May 20, 2010 | JRP sends a letter to Ontario Power Generation requesting for additional information [concerning the EIS, submitted by Ontario Power Generation in September 2009] (Source: OPG) CNSC submits 2 LTPS IRs to JRP (Source: CEAA) |
|
Ontario Power Generation responds on June 14, June 30 and August 4 to the JRP Information Request 5 of May 2010. (PDF) (Source: CEAA) |
Completed by Ontario Power Generation (OPG) |
June 14, June 30 and Aug 4, 2010 | Ontario Power Generation responds to JRP’s Information Request 5, concerning the EIS and application for a Licence to Prepare Site submitted by Ontario Power Generation in September 2009 (Source: OPG) |
|
Information Request 6: JRP letter of request for additional information (PDF) (source: CEAA) |
Completed by JRP |
June 29, 2010 | JRP sends a letter to Ontario Power Generation requesting for additional information concerning the EIS, submitted by Ontario Power Generation in September 2009 (Source: OPG) CNSC submits no new IRs to JRP |
|
Ontario Power Generation responds to the JRP Information Request 6 of June 2010. (PDF) |
Completed by Ontario Power Generation (OPG) |
August 4, 2010 | Ontario Power Generation responds to JRP’s Information Request 6, concerning the EIS and application for a Licence to Prepare Site submitted by Ontario Power Generation in September 2009] (Source: OPG) |
|
Information Request 7: JRP letter of request for additional information (PDF) (source: CEAA) |
Completed by JRP |
July 29, 2010 | JRP sends a letter to Ontario Power Generation requesting for additional information [concerning the EIS, submitted by Ontario Power Generation in September 2009] (Source: OPG) CNSC submits 1 EIS IR to JRP (Source: CEAA) |
|
Ontario Power Generation responds in August to the JRP Information Request 7 of July 29, 2010. (PDF) (Source: CEAA) |
Completed by Ontario Power Generation (OPG) |
Aug 13, 2010 | Ontario Power Generation responds to JRP’s Information Request 7, concerning the EIS and application for a Licence to Prepare Site submitted by Ontario Power Generation in September 2009 (Source: OPG) |
|
Information Request 8: JRP letter of request for additional information (PDF) (source: CEAA) |
Completed by JRP |
July 29, 2010 | JRP sends a letter to Ontario Power Generation requesting for additional information concerning the EIS, submitted by Ontario Power Generation in September 2009 (Source: OPG) |
|
| Ontario Power Generation responds to the JRP Information Request 8 of July 2010 (PDF) (source : CEAA) | Completed by Ontario Power Generation (OPG) |
August 16, 2010 | Ontario Power Generation responds to JRP’s Information Request 8 concerning the EIS and application for a Licence to Prepare Site submitted by Ontario Power Generation in September 2009 (Source: OPG) |
|
Information Request 9: JRP letter of request for additional information (PDF) (source: CEAA) |
Completed by JRP |
Sept 16, 2010 | JRP sends a letter to Ontario Power Generation requesting for additional information [concerning the EIS, submitted by Ontario Power Generation in September 2009] (Source: OPG) CNSC submits 4 IRs related to the EIS and LTPS to JRP (Source: CEAA) |
|
Ontario Power Generation responds in September and October to the JRP Information Request 9 of September 16, 2010. (PDF) (Source: CEAA) |
Completed by Ontario Power Generation (OPG) |
Sept 24 and Oct 4, 2010 | Ontario Power Generation responds to JRP’s Information Request 9, concerning the EIS and application for a Licence to Prepare Site submitted by Ontario Power Generation in September 2009 (Source: OPG) |
|
| Further Information Requests from JRP to Ontario Power Generation | CNSC completed submissions of proposed Information Requests to the JRP. Additional Information Requests from other Federal Review Teams, OPG responses and other documents, may be referenced on the CEA Registry (Source: CEAA) | |||
End of Public Comment Period Final deadline for public comments on OPG's Environmental Impact Statement and application for a Licence to Prepare a Site (Source: CEAA) |
|
October 2010 | Six-month comment period** led by JRP including review of the EIS and application for Licence to Prepare Site. Review opportunity for the JRP, public, Aboriginal groups and other stakeholders for comments. **Six-month comment period excludes time used by applicant to respond to JRP requests. The comment period is extended when there is a request for information by the JRP. The comment period’s end date considers the amount of time the applicant required to respond, and is at the discretion of the JRP. |
|
JRP public Hearing Announcement (Source: CEAA) |
|
|
December 14, 2010 | JRP has determined that the Environmental Impact Statement and the information in support of the application for a Licence to Prepare a Site, along with additional information supplied by Ontario Power Generation, has provided the Panel with enough information to proceed to a public hearing. |
JRP to hold Public Hearing News release: January 25, 2011 (Source: CEAA) New release: February, 23 2011 - Public hearing Schedule (Source: CEAA) Updated hearing schedule and list of presenters: March 16, 2011 (Source: CEAA) |
|
March 21, 2011 to April 8, 2011 | A public hearing was held from March 21, 2011 to April 8, 2011 in the Municipality of Clarington, Ontario, to hear views about the EIS and the application for a Licence to Prepare Site from the public, Aboriginal groups, Ontario Power Generation and other stakeholders. CNSC staff participated at the hearing to provide its expert opinion to the JRP concerning its review of OPG’s Environmental Impact Statement and Licence to Prepare Site application. (source: OPG). |
|
|
April 27, 2011 | The JRP gave notice that hearing participants have 20 days to submit written final comments with a deadline of May 17, 2011 |
||
Close of public record |
|
June 3, 2011 | The JRP reveived and made public all the information that it needs, including undertakings from the hearing, and therfore closed the record for the environmental assessment and is proceeding with the preparation of its environmental assessment report. |
|
JRP submits the Envionmental Assessment Report to the federal Minister of the Environment (Source : CEAA) |
|
August 25, 2011 | The Report is published and presented by the the Minister of the Environment to the Governor in Council. Subject to the Government of Canada response to the report, the Joint Review Panel may then proceed to make a decision on OPG’s Application for a Licence to Prepare Site |
|
Federal Government’s Response to Report |
Expected from the Governor in Council |
To be determined by Governor in Council | The Governor in Council responds whether the project may proceed or not. |
|
JRP issues Licence to Prepare Site |
Expected from JRP |
To be determined by JRP | If the Governor in Council’s response is that the project may proceed, the JRP could issue Licence to Prepare Site. |
|
Construction |
||||
Project Milestone |
Responsibility |
Date |
Comment |
|
CNSC and other Federal Authorities |
Applicant |
|||
Ontario Power Generation applies for Licence to Construct |
Expected from OPG |
2012 |
|
|
CNSC hold Public Hearings |
Expected from CNSC |
2014 | CNSC holds hearings on the Ontario Power Generation application for a Licence to Construct and decides on the application. |
|
Operation |
||||
Project Milestone |
Responsibility |
Date |
Comment |
|
CNSC and other Federal Authorities |
Applicant |
|||
Ontario Power Generation applies for Licence to Operate |
Expected from OPG |
2016 |
|
|
CNSC hold Public Hearings |
Expected from CNSC |
2018 | CNSC holds Public Hearings on the Ontario Power Generation application for a Licence to Operate and decides on the application |
|
Decommissioning and Abandonment |
||||
The facility is expected to undergo Decommissioning Licensing by 2076 and Abandonment Licensing by 2088. |
||||