Participating vendors and their review completion dates are outlined below. Please note that completion dates may be adjusted as needed by mutual agreement.
AECL – ACR-1000:
- Phase 1: Pre-Project Assessment of Compliance with Regulatory Requirements – December 2008
- Phase 1 Executive Summary: Pre-Project Review of AECL’s Advanced CANDU Reactor (ACR-1000) (PDF) (N.B. Due to the commercially sensitive and proprietary information in the full report, the CNSC is only able to post the Executive Summary)
- February 20, 2009 - AECL Press Release (source: AECL)
- Phase 2: Identification of Fundamental Barriers - August 2009
- Phase 2 Executive Summary: Pre-Project Review of AECL’s Advanced CANDU Reactor (ACR-1000) (PDF) (N.B. Due to the commercially sensitive and proprietary information in the full report, the CNSC is only able to post the Executive Summary)
- September 10, 2009 - AECL Press Release (source: AECL)
- Phase 1: Pre-Project Assessment of Compliance with Regulatory Requirements – January 2010
- Phase 1 Executive Summary: Pre-Project Review of Westinghouse’s Advanced Passive Plant Design (AP1000TM)
- February 5, 2010 – Westinghouse Press Release (source: Westinghouse)
AECL – EC 6 (Enhanced CANDU):
AREVA – EPR:
- Phase 1: Pre-Project Assessment of Compliance with Regulatory Requirements - To be completed in March 2010
- Phase 1: Pre-Project Assessment of Compliance with Regulatory Requirements - Review is currently on hold, at the request of the vendor
AECL - ACR-1000:
- Phase 3 Follow-up: To be completed by June 2010